Karachi April 25 2024: The National Electric Power Regulatory Authority (NEPRA) has given decision on the utility’s Transmission & Distribution Investment Plan till FY 2030 which will catalyze the company’s efforts to reduce losses in transmission and distribution, drive growth in its customer base, and bolster the power utility’s infrastructure to meet current demands and future needs.
Investment in power utility infrastructure is essential to ensure a smooth, stable, safe, and uninterrupted supply of electricity to a growing number of customers. Since privatization, investment of PKR 544 billion (equivalent to USD 2 billion ) has enabled KE to double its customer base, double the power consumption of this customer base, and more than halve its T&D losses.
The plan was submitted in accordance with regulatory guidelines and a hearing was held in March 2023 where KE management apprised stakeholders regarding the projects being planned from FY2024 to FY2030. For this period, KE has clearly identified priorities and projects for investment areas such as growth, energy loss reduction, network rehabilitation, maintenance, and safety. Digitization is also a central area of focus in these operational areas. The investment plan outlines projects to install more AMRs and implement technology such as Advanced Distribution Management Systems and Meter Data Management Systems to strengthen internal processes and introduce more transparency as well.
On the transmission front, the plan envisages the addition of grids and transmission lines which will further strengthen the reliability of KE’s network and enable the offtake of additional power from the National Grid.
Commenting on the occasion, CEO KE Moonis Alvi stated, “Over the next 7 years, we are looking to invest USD 2 billion in Transmission and Distribution to manage the city’s needs through targeted investments and tech-based interventions. I’d like to acknowledge the efforts of all stakeholders who have been a part of this journey and who will continue to work with us to modernize our infrastructure and prepare us for the future.”
The investment plan complements the company’s Power Acquisition Program through which KE has outlined its vision to achieve 30% share of renewable energy in its generation mix by 2030. In this regard the company has also received regulatory approval on RFPs of 640MW renewable projects which is another critical link in the mission to enable access to affordable energy for all.
Our teams at K-Electric are reviewing NEPRA’s decision in detail and will remain engaged with NEPRA, and as we move forward, a sustainable and cost reflective tariff remains critical for timely execution of the investment plan.
ABOUT K-ELECTRIC:
K-Electric (KE) is a public listed company incorporated in Pakistan in 1913 as KESC. Privatized in 2005, KE is the only vertically integrated power utility in Pakistan supplying electricity to Karachi and its adjoining areas. The majority shares (66.4%) of the Company are owned by KES Power, a consortium of investors including Al-Jomaih Power Limited of Saudi Arabia, National Industries Group (Holding), Kuwait, and the Infrastructure and Growth Capital Fund (IGCF). The Government of Pakistan is also a shareholder (24.36%) in the Company while the remaining shares are listed as free float shares.