Islamabad March 28 2022: Mari Petroleum Company Limited (MPCL) announce the commencement of first gas from the Tipu compartment of “Goru B” reservoir of the Mari gas field.
Initially, approximately 20 mmscfd of pipeline quality gas will be supplied to Sui Northern Gas Pipelines Limited (SNGPL) after processing at MPCL’s newly constructed Sachal Gas Processing Complex (SGPC) located in District Ghotki, Sindh.
A L S O || R E A D
Dollar reaches 184.22 as per rates issued by NBP
The gas export will take place via MPCL’s own newly built 25 km long cross country gas transmission pipeline.
The construction and commissioning activities of the remaining phases of the project are progressing satisfactorily aiming completion during the current year.