Islamabad March 9 2023: Mari Petroleum Limited inform that after successful completion of construction activities of SGPC Phase-II, the phased commissioning and performance testing of the gas processing facilities is now complete.
Presently, around 95 Million Standard Cubic Feet per Day (MMSCFD) of pipeline specification gas is being supplied to SNGPL via MPCL’s own 20 inch, 25 km long, cross country gas transmission pipeline connecting SGPC to the SNGPL valve assembly (QV-2) at Muhammadpur.
Post integration of SGPC Phase-I & II and after commissioning of the remaining wells which is ongoing, the plant will reach its full potential in due course.